Planned
Garbhagriha silver door replacement
The 1990s silver sheet on the garbhagriha doors has worn through at the handles.
- Carried out by
- Sarafa silversmiths under the samiti’s supervision
- Sanctioned budget
- ₹12,50,000
- Timeline
- 20 Jan 2027 – 5 Mar 2027
- Original form
- Unchanged
In progress
Annakshetra kitchen expansion
Daily meals have grown to ~2,000; the kitchen was built for 500.
- Carried out by
- PWD, Indore
- Sanctioned budget
- ₹38,00,000
- Timeline
- From 1 Jun 2026
- Original form
- Unchanged
Progress updates
Main structure is up; finishing work and painting are in progress.
Foundation and base work completed; material for the next stage has arrived.
Completed
Queue shed with fans (east gate)
No shade for devotees queueing in summer.
- Carried out by
- Shri Balaji Fabricators, Indore
- Sanctioned budget
- ₹6,40,000
- Timeline
- 1 Mar 2026 – 15 Apr 2026
- Original form
- Unchanged
Progress updates
Work completed and handed over to the temple; the site has been cleaned.