Planned
Gopuram stucco repainting
Painted stucco panels on the gopuram have faded and flaked.
- Carried out by
- Artisans from Mahabalipuram via the trust
- Sanctioned budget
- ₹18,00,000
- Timeline
- 1 Dec 2026 – 28 Feb 2027
- Original form
- Unchanged
Completed
Pravachan hall sound system
Old PA system unreliable during discourses.
- Carried out by
- Shri Sai Sound, Indore
- Sanctioned budget
- ₹2,60,000
- Timeline
- 1 Jul 2026 – 10 Jul 2026
- Original form
- Unchanged
Progress updates
Work completed and handed over to the temple; the site has been cleaned.
Foundation and base work completed; material for the next stage has arrived.